StPaul-Millington.org Interactive

September 28, 2009

Final Product

Filed under: Building Status Update — Webmaster @ 9:07 pm

August 28, 2009

Bleachers

Filed under: Building Status Update — Webmaster @ 4:41 pm

The bleachers are almost complete.

This image (actually 3) show what it looked like from the top before the green seats were installed.

August 14, 2009

Center Court

Filed under: Building Status Update — Webmaster @ 12:03 pm

In this image you can see the stencil being installed for the center court logo.

In this image the colors have been painted.

Here it is with the stencil removed.  Now they have to finish the rest of the green main court lines.

August 11, 2009

Giant Stencils

Filed under: Building Status Update — Webmaster @ 8:50 pm

In this image you can start to see the boarders for the lines being installed.

Here is a closer view of some of the lines being outlined.

In this image you can see the floor painter splicing together the stencil for the center logo.

August 9, 2009

New Entrance Way, and More Floor

Filed under: Building Status Update — Webmaster @ 5:04 pm

This image shows the new entrance way to the church office area.  It’s not really part of the building project, but it was added at the same time.  This new set of doors along with the new pitched roof over this section of the building will make it more energy efficient.

This image shows the wood floor complete with one coat of sealer on the entire thing.  Near the far wall you can see the second coat of sealer being completed. Painting of the lines will be the next step.

July 31, 2009

The Maple Sea?

Filed under: Building Status Update — Webmaster @ 10:21 am

As you can see the wood floor is nearing completion. About 10 feet needs to be finished under the bleacher area.  You can see this in the lower left corner of the picture.  The orange cone is covering an electrical box mounted in the floor near the front edge of the bleachers.

The ceiling tile has been installed in the locker rooms, bathrooms, and hall areas.  You can see some of it in this image.

July 23, 2009

Update

Filed under: Building Status Update — Webmaster @ 9:57 pm

They have started painting the parish hall.

The lockers have been installed.  There are 36 in each locker room.

Look at the nice wood floor.  I know this picture doesn’t give a good view of the progress, but it does show how nice and flat it is.  They at least doubled what was done yesterday.

July 22, 2009

More Floor

Filed under: Building Status Update — Webmaster @ 10:11 pm

Day 3 progress.

Another view.

July 21, 2009

Plywood Floor

Filed under: Building Status Update — Webmaster @ 9:05 pm

This image shows day one of the plywood layers going down.

This images shows day two. (Today)

Here is another view of today’s progress.

The fire extinguisher was also installed today.

July 13, 2009

Backboards

Filed under: Building Status Update — Webmaster @ 9:38 pm

They finished up the rest of the supports (now all 6 are installed) and finished hanging the backboards and completed the cabling and safety belts.  Now all that is left is the rims and padding.  This floor should start going down Wednesday.

Older Posts »

Powered by WordPress