This image is looking into the enterance area.

This image shows the space behind the plastic tarping this space will make up the bathrooms and locker rooms. They are actually working between this wall and the tarp.

This image shows more of the roof panels going on.

This image shows the progress on the “back” of the building, where the mechanical and electrical rooms will be along with a little activities storage.

Now that the weather has warmed up a little some more progress is being made. In the above image you can see the entrance way begining to take shape.

This is another view of the enterance way. The doors will be to the left of this image, and to the right of the mini wall with orange toppers on it will be some windows.

The gap in the back wall has been filled up. The holes that you see in the back wall that are not doors, will be for the ventilation system.
Check back soon, as now that the weather is not so frigid cold, progress will start picking back up.

This view does not show you much of the new building project, but it does show some of the new roof.

This image is looking toward the town of Millington. You can see the finished trusses. No, I am not standing on the steel trusses, the other half of the roof is covered with the tectum deck sandwitch.

If you look off in the distance you can see the Millington water tower.

This is a close up view of the cross. If you look to the right of the image you can see the entire wall down to the what will be the floor of the Activities Center.

For those of you that were wondering what was going on uder the large scafold tent. Here is the left wall of the entry way in the forground. The wall was hard to photograph with all the scafolding, but that should be comming down soon as it looks complete. I will take more pictures there.