As you can see the wood floor is nearing completion. About 10 feet needs to be finished under the bleacher area. You can see this in the lower left corner of the picture. The orange cone is covering an electrical box mounted in the floor near the front edge of the bleachers.

The ceiling tile has been installed in the locker rooms, bathrooms, and hall areas. You can see some of it in this image.

They have started painting the parish hall.

The lockers have been installed. There are 36 in each locker room.

Look at the nice wood floor. I know this picture doesn’t give a good view of the progress, but it does show how nice and flat it is. They at least doubled what was done yesterday.

This image shows day one of the plywood layers going down.

This images shows day two. (Today)

Here is another view of today’s progress.

The fire extinguisher was also installed today.

They finished up the rest of the supports (now all 6 are installed) and finished hanging the backboards and completed the cabling and safety belts. Now all that is left is the rims and padding. This floor should start going down Wednesday.

In this image you can see the first of the basketball backboard supports being installed.

The light controller has been programmed so the lights will automatically turn off at specified times to save energy and meet regulations for energy savings.

The locker rooms are ready for lockers.

This image isn’t the best quality (it’s hard to take pictures in the dark without a tripod), but it shows what it would look like outside with out the exterior lights on.

In this image you can see that the ceiling grids have been installed in the main entrance area.

This image shows more ceiling grids, and boxes and boxes of ceiling tiles ready to be installed.